Who Gets to Build Eskom’s Next 6GW of Green Power

Posted on November 24, 2026
22

South African developers spent years building wind and solar farms to the sizes government asked for. Now those same developers could struggle to lead bids for Eskom’s next round of green power projects. According to Daily Maverick, energy analyst Chris Yelland says the obstacle is the size of a single power plant.

Eskom wants lead bidders to show experience on at least one operating project of 240MW or more. For years, government typically capped individual solar projects at 75MW and wind farms at 140MW. Yelland argues that companies with larger projects overseas have an advantage because Eskom accepts experience gained anywhere in the world.

Why one plant matters

According to Daily Maverick, a lead bidder or its controlling parent must meet two separate tests. It needs at least 800MW across its operating portfolio, and one project must meet the 240MW threshold. Several smaller plants at the same site cannot be counted as one. A project still under construction does not count towards that threshold either.

SOLA Group illustrates the gap. According to Yelland’s analysis in Daily Maverick, the company has about 600MW in operation. Its largest plant, Springbok, is 195MW. That leaves it 45MW short on the single-project test, even with experience across several plants.

What’s at stake for local developers

According to Eskom, the utility is choosing a panel of partners for five years. Those partners may be invited to bid for individual projects under a programme covering up to 6GW of renewable energy and storage. Eskom plans to contribute at least 2GW of solar projects and 1GW of battery storage.

Local developers can still join a group led by a company that qualifies. The concern, according to Daily Maverick, is that South African firms could bring projects and expertise to the table while an overseas partner leads the bid and holds the relationship with Eskom.

Eskom says it needs partners with the technical experience and financial resources to build and operate projects at this scale. According to Daily Maverick, Eskom told bidders it had no intention of excluding local producers from leading bids. It kept the 240MW requirement.

According to Eskom’s tender notice, companies have until 30 November 2026 to submit questions. Applications close at 10am on 12 January 2027.

Recent Posts

  • Madlanga Commission forced to adjourn over Witness T safety fears
  • Who Gets to Build Eskom’s Next 6GW of Green Power
  • BREAKING NEWS The #MadlangaCommission has postponed Witness T’s remote, parti…
  • eThekwini council sworn in, then paused as coalition talks take over
  • Orlando Pirates star: From potential to key pillar!

First established in 2020 by iReport Media Group, southafricanlive.co.za has evolved to become one of the most-read websites in South Africa. Published by iReport Media Group since 2020, find out all about us right here.

We bring you the latest breaking news updates, from South Africa and the African continent. South African Live is an independent, no agenda and no bias online news disruptor that goes beyond the news and behind the headlines. We believe what sets us apart is that we deliver news differently. While we hold ourselves to the utmost journalistic integrity of being truthful, we encourage a writing style that is acerbic and conversational, when appropriate.

LATEST NEWS

  • Madlanga Commission forced to adjourn over Witness T safety fears
  • Who Gets to Build Eskom’s Next 6GW of Green Power
  • BREAKING NEWS The #MadlangaCommission has postponed Witness T’s remote, parti…
  • eThekwini council sworn in, then paused as coalition talks take over
  • Orlando Pirates star: From potential to key pillar!

Menu

  • Entertainment
  • Business
  • Politics
  • Tech
  • Fashion
  • Sports
  • About us
©2026 South African Live | Design: Newspaperly WordPress Theme